試題1
假設(shè)某計(jì)算機(jī)系統(tǒng)中資源R的可用數(shù)為6,系統(tǒng)中有3個(gè)進(jìn)程競(jìng)爭(zhēng)R,且每個(gè)進(jìn)程都需要i個(gè)R,該系統(tǒng)可能會(huì)發(fā)生死鎖的最小i值是 (24) 。若信號(hào)量S的當(dāng)前值為-2,則R的可用數(shù)和等待R的進(jìn)程數(shù)分別為 (25) 。查看答案
試題參考答案:C、D
試題2
某軟件項(xiàng)目的活動(dòng)圖如下圖所示,其中頂點(diǎn)表示項(xiàng)目里程碑,連接頂點(diǎn)的邊表示包含的活動(dòng),邊上的數(shù)字表示活動(dòng)的持續(xù)時(shí)間(天)。完成該項(xiàng)目的最少時(shí)間為()天。由于某種原因,現(xiàn)在需要同一個(gè)開發(fā)人員完成BC和BD,則完成該項(xiàng)目的最少時(shí)間為()天。
查看答案
試題參考答案:B、C
試題3
對(duì)于一個(gè)初始無(wú)序的關(guān)鍵字序列,在下面的排序方法中,( )第一趟排序結(jié)束后,一定能將序列中的某個(gè)元素在最終有序序列中的位置確定下來(lái)。查看答案
試題參考答案:C
試題4
某快餐廳主要制作并出售兒童套餐,一般包括主餐(各類比薩)、飲料和玩具,其餐品種類可能不同,但制作過(guò)程相同。前臺(tái)服務(wù)員(Waiter) 調(diào)度廚師制作套餐。欲開發(fā)一軟件,實(shí)現(xiàn)該制作過(guò)程,設(shè)計(jì)如下所示類圖。該設(shè)計(jì)采用( )模式將一個(gè)復(fù)雜對(duì)象的構(gòu)建與它的表示分離,使得同樣的構(gòu)建過(guò)程可以創(chuàng)建不同的表示。其中,( )構(gòu)造一個(gè)使用Builder接口的對(duì)象。該模式屬于( )模式,該模式適用于( )的情況。查看答案
試題參考答案:A 、C 、A 、D
試題5
進(jìn)程P1、 P2、P3、P4、P5和P6的前趨圖如下所示。用PV操作控制這6個(gè)進(jìn)程之間同步與互斥的程序如下,程序中的空①和空②處應(yīng)分別為(1),空③和空④處應(yīng)分別為(2), 空⑤和空⑥處應(yīng)公別為(3)
(1)A、V(S1)和P(S2)P(S3)
B、V(S1)和V(S2)V(S3)
C、P(S1)和P(S2)V(S3)
D、P(S1)和V(S2)V(S3)
(2)A、V(S3)和P(S3)
B、V(S4)和P(S3)
C、P(S3)和P(S4)
D、V(S4)和P(S4)
(3)A、V(S6)和P(S5)
B、V(S5)和P(S6)
C、P(S5)和V(S6)
D、P(S5)和V(S5)
查看答案
試題參考答案:D、B、A
試題6
TCP使用的流量控制協(xié)議是( )。
A.固定大小的滑動(dòng)窗口協(xié)議
B.后退N幀的ARQ協(xié)議
C.可變大小的滑動(dòng)窗口協(xié)議
D.停等協(xié)議
查看答案
試題參考答案:C
試題7
A project is a [temporary] ( 1 )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to ( 2 )。
Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n) ( 3 ) system at a minimum cost within a specified time frame、
For any systems development project,effective project management is necessary to ensure that the project meets the ( 4 ) ,is developed within an acceptable budget,and fulfills customer expectations and specifications、Project management is a process that starts at the beginning of a project,extends through a project,and doesn’t culminate until the project is completed、
The prerequisite for good project management is a well-defined system development process、Process management is an ongoing activity that documents,manages the use of,and improves an organization’s chosen methodology (the“process”) for system development、Process management is concerned with the activities,deliverables,and quality standards to be applied to ( 5 ) project(s)、
(1)A、task
B、work
C、sequence
D、activity
(2)A、specifications
B、rules
C、estimates
D、designs
(3)A、perfect
B、acceptable
C、controlled
D、completed
(4)A、deadline
B、specification
C、expectation
D、requirement
(5)A、asingle
B、aparticular
C、some
D、all
查看答案
試題參考答案:C、A、B、A、D
試題8
某計(jì)算機(jī)系統(tǒng)由下圖所示的部件構(gòu)成,假定每個(gè)部件的千小時(shí)可靠度都為 R ,則
該系統(tǒng)的千小時(shí)可靠度為 ( ) 。
A. A
B. B
C. C
D. D
查看答案
試題參考答案:D
試題9
下列設(shè)計(jì)模式中,(46)模式既是類結(jié)構(gòu)型模式,又是對(duì)象結(jié)構(gòu)型模式。此模式與(47)模式類似的特征是,都給另一個(gè)對(duì)象提供了一定程度上的間接性,都涉及到從自身以外的一個(gè)接口向這個(gè)對(duì)象轉(zhuǎn)發(fā)請(qǐng)求。查看答案
試題參考答案:B、A
試題10
某簡(jiǎn)單無(wú)向連通圖G的頂點(diǎn)數(shù)為n,則圖G最少和最多分別有( )條邊。查看答案
試題參考答案:B
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |