A portion of a project’s work will be procured from an external source. The project team creates statement for the procurement plan and issues a request for proposal to multiple suppliers. Project team questions about the work from the prospective suppliers. What should the project team do to provide responses to prospective suppliers ?
A、Send out individual responses to each supplier.
B、Designate a single point of contact for each suppliers from the project team to handle questions.
C、Revise the request for proposal to include responses to all questions and circulate to all suppliers.
D、Hold bidder conferences to clarity all questions across all suppliers.
我的答案與分析 查看全部答題與分析 | |
|
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。