A project manager for a bidding project receives preliminary information from the client in project early stage. The client
requests a fixed-price contract for the entire project. What should the project manager do
A. Estimate the project based on similar project, explain the assumptions, and present a change management plan to the client to
protect the estimate from future scope changes.
B. Estimate the project based on similar protects, and add a reasonable amount of risk contingency to protect the estimate from future
scope changes.
C. Estimate the clearly defined requirements, and present this as a fixed-price compacts to the first part of the project.
D. Estimate the project based on the information available, and initiate claims immediately as soon as any scope changes appear.
我的答案與分析 查看全部答題與分析 | |
|
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。