1、 ( ) is primarily concerned with defining and controlling what is and is not included in the project.
A. Project Time Management
B. Project Cost Management
C. Project Scope management
D. Project Communications Management
信管網(wǎng)參考答案:C
《系統(tǒng)集成項(xiàng)目管理工程師教程》第七章項(xiàng)目范圍管理:范圍管理確定在項(xiàng)目?jī)?nèi)包括什么工作和不包括什么工作,由此界定的項(xiàng)目范圍在項(xiàng)目的全生命周期內(nèi)可能因種種原因而變化,項(xiàng)目范圍管理也要管理項(xiàng)目范圍的這種變化。
查看解析:http://m.xiexiliangjiufa.com/st/1242.html
2、 A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A.a(chǎn)ssign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
信管網(wǎng)參考答案:D
項(xiàng)目經(jīng)理認(rèn)為,修改項(xiàng)目范圍可以為客戶提供增值服務(wù)。項(xiàng)目經(jīng)理應(yīng)該()。
A、 將更改任務(wù)分配給項(xiàng)目成員
B、 召開(kāi)配置控制委員會(huì)會(huì)議
C、 更改范圍基線
D、 推遲修改,直到根據(jù)原始基線完成此項(xiàng)目后,為單獨(dú)的增強(qiáng)項(xiàng)目提供資金
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |