A senior manager responsible for business transaction identified a system requirement to control the trading risks. The senior manager drafts document required to demonstrate rationality and establish boundaries for the project. A senior manager asks the project manager to starts project planning immediately. What should the project manager do first?
A、 Identify stakeholders.
B、 Develop project charter
C、 Define the project scope.
D、 Write a business case.