At a project status team meeting, one team member disagrees with another team member regarding a corrective action. The debate escalates and they are soon both adamantly, Other team members are not participating. The project manager directs the team on the corrective action to use.  What conflict resolution technique did the project manager use ?
A、Compromising
B、Forcing
C、Withdrawing
D、Smoothing