試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During an informal conversation with a project team member,the project manager discovers that a supplier for a key part has problems implementing an approved product change. Which of the following should the project manager do next ?
A、Perform a quality audit of the supplier.
B、Schedule a change control meeting.
C、Measure the supplier’s work performance.
D、Speak with a senior manager of the supplier.