試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You are the project manager for a large government contract. The contract was signed a year ago for this tree-year, mufti-million-dollar project. You were not involved in writing the contract or setting up change control procedures, but now you are being inundated with change requests from the project sponsor and from your own senior management. What should you do first ?
A、Tell the sponsor and your senior management that any changes are out of scope at this point and cannot be considered.
B、 Meet with the project sponsor and senior management to discuss this problem and potential solutions.
C、 Talk to your legal department to make sure you doesn’t do anything illegal.
D、 Ask senor management to set aside more management reserve to avoid potential financial problems.