女人久久久www免费人成看片,国内自拍偷拍网,国产一区二区三区免费在线观看,欧美精品三区四区,91久久国产综合久久91,欧美成人精品第一区二区三区 ,美女成人在线观看

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager conducts an interview with a key stakeholder. This stakeholder insists that the project be completed by a certain date to allow the resulting product to be arranged manufacture in time for a critical trade exhibition. The stakeholder also insists that the product must pass existing international safety standards. The stakeholder will not release the initial fund for the project kick-off unless both conditions are included.  Where must the project manager include these conditions?
A、Project summary milestones
B、 Project contract summary
C、 Project high-level requirements
D、 Project exit criteria


相關(guān)試題

推薦文章