女人久久久www免费人成看片,国内自拍偷拍网,国产一区二区三区免费在线观看,欧美精品三区四区,91久久国产综合久久91,欧美成人精品第一区二区三区 ,美女成人在线观看

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

During the project performance is reviewed, the project manager identifies some activities that cannot be completed on time, because of poor team performance. What would be next step ?
A、Offer rewards for team members willing to work overtime to meet project needs.
B、 Look for root causes that may be affecting team performance.
C、 Review the schedule to align it to current team performance.
D、 Promise training sessions to increase team performance.


相關試題

推薦文章
合作網站內容