女人久久久www免费人成看片,国内自拍偷拍网,国产一区二区三区免费在线观看,欧美精品三区四区,91久久国产综合久久91,欧美成人精品第一区二区三区 ,美女成人在线观看

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager is in the process of documenting the results of a team member’s work to ensure that the team member has met all of the requirements and specifications. What is the project manager actually doing ?
A、Performing administrative closure activities.
B、Completing lessons learned.
C、Completing the requirements specification document.
D、Updating the issues log.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容