試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

At the project closure, one of the contracts is still open because the customer is on a business trip. The project manager is already assigned to new project and must close this project as soon as possible. What should the project manager
A、Close the project and pass the contract to the company’s finance department
B、Close the project but have the contract under the project manager’s supervision until the project is closed
C、Delay the project closure and stay on it until the contract is formally signed and closed
D、Ask the PMO to assign a temporary project manager for this project until the contract is closed