女人久久久www免费人成看片,国内自拍偷拍网,国产一区二区三区免费在线观看,欧美精品三区四区,91久久国产综合久久91,欧美成人精品第一区二区三区 ,美女成人在线观看

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project health check identified a risk that your project would not be completed on time. Several projects are competing for the same resources, and a serious resource conflict is emerging. As a result, you are quantifying the project’s risk exposure and determining what cost and schedule contingency reserves might be needed. You performed a schedule risk analysis using Monte Carlo analysis. The basis for your schedule risk analysis is the:
A、WBS
B、Gantt chart
C、Schedule network diagram and duration estimates
D、Probability/impact risk rating matrix


相關試題

推薦文章
合作網(wǎng)站內(nèi)容