A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.There are some special activities called (72) . which are events that signify the ccomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73), whose purpose is to contain the various pieces of relevant information - feasibility assessments,schedules, needs analysis, and so forth - in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
(71) A. Structure Chan
B. Organizational Structure
C. Work Breakdown Structure
D. Functional decomposition diagram
(72) A. feasibility checkpoints
B. milestones
C. iterations
D. phases
(73) A. statement of work
B. project planning
C. baseline plan
D. information system planning
(74) A. Network Diagram
B. CPM
C. Gantt chart
D. PERT
(75) A. Gantt chart
B. Network Diagram
C. PERT
D. CPM
我的答案與分析 查看全部答題與分析 | |
|
信管網訂閱號
信管網視頻號
信管網抖音號
溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網軟考課程由信管網依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。