71、After acceptance and formal transfer of information systems to customers it has entered the stage of ()
A、preparation
B、operation and maintenance
C、development
D、extinction
信管網(wǎng)參考答案:B
72、()a method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it
A、prototype
B、object oriented
C、structured method
D、iterative method
信管網(wǎng)參考答案:A
73、The scope management plan is how the team will prepare the()a document that includes
descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A.project charter
B.project scope goal
C.project budget
D.project scope statement
信管網(wǎng)參考答案:D
74、( ) is one of the tools and techniques of Sequence Activities
A.Decomposition
B.Fishbone Diagram
C.Precedence Diagramming Method
D.Expert Judgment
信管網(wǎng)參考答案:C
75、The schedule management plan is a component of the project management plan The
schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the () of the project, and includes appropriate control thresholds.
A.goals
B.values
C.needs
D.level
信管網(wǎng)參考答案:C
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |