試題1
隨著時(shí)代的發(fā)展,社會(huì)的進(jìn)步,越來(lái)越多的軟件和互聯(lián)網(wǎng)項(xiàng)目進(jìn)入到了你所在公司的業(yè)務(wù)范圍。公司意識(shí)到,傳統(tǒng)的瀑布管理模型已經(jīng)越來(lái)越難以應(yīng)對(duì)瞬息萬(wàn)變的互聯(lián)網(wǎng) 所以安排了項(xiàng)目進(jìn)行敏捷的轉(zhuǎn)型。作為敏捷管理專業(yè)人士,公司高層來(lái)征詢你對(duì)敏捷轉(zhuǎn)型的意見(jiàn),請(qǐng)問(wèn)以下哪一個(gè)現(xiàn)象能夠支持公司向敏捷轉(zhuǎn)型?查看答案
試題參考答案:D
試題2
A project has a schedule performance index(SPI)of 1.2 for all project work,and an SPI of0.8 for the critical path.How should the project manager classify this project查看答案
試題參考答案:C
試題3
在某設(shè)備制造和安裝項(xiàng)目的執(zhí)行階段,賣方所在城市機(jī)場(chǎng)的員工罷工,導(dǎo)致設(shè)備不能按時(shí)啟運(yùn)。根據(jù)項(xiàng)目的進(jìn)度計(jì)劃,設(shè)備運(yùn)輸是關(guān)鍵路徑上的活動(dòng)。在這種情況下,買方最好如何做()。查看答案
試題參考答案:A
試題4
在項(xiàng)目執(zhí)行期間.有必要終止一個(gè)供應(yīng)商的合同.項(xiàng)目經(jīng)理下一步應(yīng)該怎么做?查看答案
試題參考答案:B
試題5
建筑師指出一座新建筑物的嚴(yán)重設(shè)計(jì)缺陷,并提供了新的設(shè)計(jì),許多團(tuán)隊(duì)成員也都提出其他選擇方案,不過(guò),總建筑師卻不愿意考慮這些方案。這屬于哪種沖突解決方法?查看答案
試題參考答案:C
試題6
某項(xiàng)目多個(gè)風(fēng)險(xiǎn)發(fā)生概率和對(duì)成本、進(jìn)度、績(jī)效的影響如下∶查看答案
試題參考答案:D
試題7
某個(gè)延期項(xiàng)目的客戶請(qǐng)求增加功能。該功能可以在不對(duì)進(jìn)度或成本產(chǎn)生重大影響的情況下嵌入。項(xiàng)目經(jīng)理下一步該怎么做?查看答案
試題參考答案:D
試題8
A complex project comprises stakeholders with differing views on the final objective.Ultimately,the stakeholders agree o n the objective defined by the project sponsor.The sponsor then retires during the execution phase,which begins to create conflict among stakeholders. The newly appointed sponsor w ants to know what can be done to realign stakeholders with t he objective. What should the project manager do查看答案
試題參考答案:D
試題9
You are going to launch a new product in the market and to attract customers you sign an advertisement contract with a famous Hollywood actor. What kind of power are you using he re to market your product?查看答案
試題參考答案:B
試題10
During initial project acceptance,the customer is satisfied with project performance. However,they ask to move the delivery date forward by one week and explain their reason t o the project manager. What should the project manager do n ext?查看答案
試題參考答案:D
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |