試題1
在執(zhí)行階段外部供應(yīng)商的員工在月底要罷工,在收到該消息時(shí),項(xiàng)目經(jīng)理應(yīng)該首先更新下列哪一項(xiàng)?查看答案
試題參考答案:C
試題2
項(xiàng)目經(jīng)理與兩名持相反觀點(diǎn)的團(tuán)隊(duì)成員開會(huì)。在會(huì)議中,項(xiàng)目經(jīng)理根據(jù)兩人的意見,最終采取了一個(gè)折中的方案。項(xiàng)目經(jīng)理采用的是哪種沖突管理技術(shù)?查看答案
試題參考答案:D
試題3
在本季度末,項(xiàng)目的完工尚需績(jī)效指數(shù)(TCPD)為1.3,項(xiàng)目經(jīng)理必須創(chuàng)建成本應(yīng)急計(jì)劃,造成這種結(jié)果的原因是什么?查看答案
試題參考答案:B
試題4
一個(gè)團(tuán)隊(duì)決定敏捷方法是否適合他們項(xiàng)目下一階段的需求。不利的是,有些團(tuán)隊(duì)成員沒有接受過(guò)適當(dāng)?shù)拿艚菖嘤?xùn)。項(xiàng)目經(jīng)理應(yīng)該如何應(yīng)對(duì)敏捷培訓(xùn)的缺乏?查看答案
試題參考答案:D
試題5
公司正在根據(jù)現(xiàn)代質(zhì)量管理方法來(lái)制定項(xiàng)目質(zhì)量方針,其中哪項(xiàng)不需要考慮?查看答案
試題參考答案:D
試題6
項(xiàng)目經(jīng)理在項(xiàng)目啟動(dòng)階段加入一個(gè)新產(chǎn)品開發(fā)項(xiàng)目,項(xiàng)目經(jīng)理首先應(yīng)該怎么做?查看答案
試題參考答案:A
試題7
A project is seriously delayed. Earned value analysis shows t hat the project needs to be completed 10 percent faster than t he work has been going. To get the project back on track,management wants to add 10 people to an activity currently assigned to one person. The project manager disagrees,noting that such an increase will not produce an increase in speed. This is an example of:查看答案
試題參考答案:A
試題8
A company was acquired by a big company that wanted to focus on its core products and services.The projects in the planning phase are being revised to include the new change management process. The project manager of a project needs continuous high-level input to ensure consistency with the new organizational structure. What should the project manager do to ensure that project changes are managed effectively?A. Reopen the requirements, expand the project to include the new change management process, and designate a team member to take full respons1bility for change management. B.Determine which change controls apply to the project, implement only those relevant and查看答案
試題參考答案:D
試題9
A conflict occurs between team member A and team member B in a project. The project manager calls both team members together and examines different solutions to the issue. Which of the following techniques does the project manager use to resolve the conflict?()查看答案
試題參考答案:A
試題10
下列四個(gè)選項(xiàng)中,屬于規(guī)劃范圍管理的輸出的是∶查看答案
試題參考答案:A
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |