試題1
項(xiàng)目團(tuán)隊(duì)通過(guò)多個(gè)比較因素,展示各因素、原因和目標(biāo)之間的關(guān)系強(qiáng)弱,以便識(shí)別出對(duì)項(xiàng)目成功至關(guān)重要的質(zhì)量測(cè)量指標(biāo),團(tuán)隊(duì)正在使用:查看答案
試題參考答案:C
試題2
一個(gè)產(chǎn)品按時(shí)按成本交付,并滿足質(zhì)量期望。但是項(xiàng)目團(tuán)隊(duì)不確定生產(chǎn)的產(chǎn)品是否符合需求。下列哪項(xiàng)說(shuō)明了這種情況?查看答案
試題參考答案:D
試題3
當(dāng)賣(mài)方在執(zhí)行一個(gè)成本補(bǔ)償合同時(shí),買(mǎi)方?jīng)Q定增加服務(wù)范圍,并變更為固定總價(jià)合同。以下都是賣(mài)方的選擇,除了∶查看答案
試題參考答案:D
試題4
哪個(gè)理論認(rèn)為,個(gè)人不同程度上的成就需要、權(quán)力需要、親和需要,三種需要行為,管理者應(yīng)該根據(jù)個(gè)人更重視的需要來(lái)制定激勵(lì)措施:查看答案
試題參考答案:A
試題5
A project is unable to assign a subject matter expert (SME). The team is concerned that due to the absence of an SME,incorrect assumptions will lead to rework. What should the project manager do?查看答案
試題參考答案:B
試題6
某工廠目前的銷售額為200萬(wàn)元,希望通過(guò)擴(kuò)建廠房提高產(chǎn)量和銷量。在風(fēng)險(xiǎn)分析過(guò)程中,認(rèn)為擴(kuò)建廠房后,市場(chǎng)情況有很大的不確定性。市場(chǎng)好的可能性為45%,銷售額增長(zhǎng)60%; 市場(chǎng)較差的可能性為20%,銷售額會(huì)減少30%;市場(chǎng)一般的可能性為35%,銷售額增加20%。試問(wèn)擴(kuò)建廠房項(xiàng)目的EMV值為多少?查看答案
試題參考答案:A
試題7
在一次團(tuán)隊(duì)會(huì)議上,屬于主題專家(SME)的成員提到他們不斷為重復(fù)任務(wù)工作,導(dǎo)致積極性降低。敏捷項(xiàng)目管理師應(yīng)該怎么做?查看答案
試題參考答案:B
試題8
During a project's execution phase,a vendor failed to deliver specified materials on time.This delayed a project's activity. What should the project manager do next?查看答案
試題參考答案:A
試題9
A company plans to expand the service scope of its corporate website. The project manager starts to collect detailed requirements based on the approved project charter. What should t he project manager do to reach a group consensus on the project's deliverabies?查看答案
試題參考答案:B
試題10
A team member is responsible for guiding a contractor on a project deliverable. The team member tells the contractor that the deliverable must be redone.The contractor issues a bill fo r the addition work. What should the project manager do 一位團(tuán)隊(duì)成員負(fù)責(zé)指導(dǎo)承包商的項(xiàng)目可交付成果相關(guān)工作,該團(tuán)隊(duì)成員告訴承包商部分可交付成果必須返工承包商簽發(fā)了一份額外工作的賬單。項(xiàng)目經(jīng)理應(yīng)該做什么查看答案
試題參考答案:B
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |