PMP?當天每日一練試題地址:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=33
往期PMP?每日一練試題匯總:m.xiexiliangjiufa.com/class/27/e33_1.html
PMP?每日一練試題(2022/11/3)在線測試:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=33&day=2022/11/3
點擊查看:更多PMP?習(xí)題與指導(dǎo)
PMP?每日一練試題內(nèi)容(2022/11/3)
試題1
Stakeholders claims that a feature is missing from a deliverable.This feature,was not mentioned in any prior discussions.and was not included in the acceptance criteria however.the stakeholders insist that the feature is necessary to take full advantage of the deliverable, What should the project manager do?查看答案
試題參考答案:A
試題2
The sponsor asks the project manager to provide a cost estimate for a potential new project. Project funding cannot exceed US$400.000.If the rough order of magnitude (ROM) rang e is estimated between US$375,000 and US$875,000,what should the project manager advise the sponsor?查看答案
試題參考答案:B
試題3
一個項目涉及位于全球各地的團隊成員,產(chǎn)生了許多不同意見,新項目經(jīng)理通過成功促進團隊協(xié)作和問題解決提高生產(chǎn)力,項目經(jīng)理使用的是什么工具或技術(shù)?查看答案
試題參考答案:A
試題4
一個涉及新技術(shù)采購、多個位置、虛擬團隊和外部供應(yīng)商的復(fù)雜項目已成功完成。項目經(jīng)理下一步應(yīng)該怎么做?查看答案
試題參考答案:B
試題5
A project manager has a project that is constantly facing challenges. The sponsor is regularly unavailable to make decisions, there are massive budget overruns, team members are constantly leaving the project,and there is no practical support provided by senior management. What should the project manager do?查看答案
試題參考答案:A
試題6
在項目施工階段,項目發(fā)起人決定對內(nèi)部設(shè)計進行重大修改。項目經(jīng)理通過一對一的方式獲取相關(guān)需求,這屬于哪項技術(shù)?查看答案
試題參考答案:C
試題7
A project manager assumes a project during its execution stage and wants to review the project scope for cost settlement. The project manager discovers that some deliverables were missed in the work breakdown structure(WBS).What should the project manager do first?查看答案
試題參考答案:C
試題8
In a construction project, the project manager notices that the y can save $10 million if they use a different mounting system. What should be the project manager's reaction?查看答案
試題參考答案:C
試題9
成本補償合同的例行審計中發(fā)現(xiàn)賣方過度報銷費用。如果合同中沒有定義相應(yīng)的糾正措施,買方應(yīng)該怎么做?查看答案
試題參考答案:A
試題10
有效的溝通對于項目的成功至關(guān)重要。范圍變更、限制條件、假設(shè)、整合與界面要求,重疊的角色和責任以及其它許多因素都對溝通提出了挑戰(zhàn)。溝通上的障礙很可能導(dǎo)致∶查看答案
試題參考答案:D
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |