PMP?每日一練試題內(nèi)容(2022/11/4)
試題1
由于范圍蔓延,項(xiàng)目團(tuán)隊(duì)成員必須工作更長的時(shí)間,這導(dǎo)致他們士氣低下。在下一次項(xiàng)目評(píng)審會(huì)議上,項(xiàng)目經(jīng)理應(yīng)該采取下列哪項(xiàng)措施?()查看答案
試題參考答案:D
試題2
你們?cè)跒槊绹茉床孔鲆粋€(gè)項(xiàng)目,采用掙值分析作為績效報(bào)告技術(shù)?,F(xiàn)在項(xiàng)目已經(jīng)完成了20%,掙值分析的結(jié)果顯示 CPI為 0.67,SPI0.87。在這種情況下,你應(yīng)該∶查看答案
試題參考答案:D
試題3
當(dāng)前項(xiàng)目進(jìn)度落后于計(jì)劃,高級(jí)經(jīng)理表示項(xiàng)目必須按時(shí)完成。項(xiàng)目經(jīng)理基于歷史數(shù)據(jù)和項(xiàng)目參數(shù),計(jì)算出按時(shí)完成項(xiàng)目所需的資源數(shù)量,他應(yīng)該使用哪個(gè)文件向高級(jí)經(jīng)理進(jìn)行展示?查看答案
試題參考答案:C
試題4
你剛剛在啟動(dòng)大會(huì)上被任命為項(xiàng)目經(jīng)理,項(xiàng)目章程中要求整個(gè)項(xiàng)目要在2018年10月15日這個(gè)里程碑完工。某個(gè)重要相關(guān)方認(rèn)為項(xiàng)目完工日期會(huì)錯(cuò)過十一黃金周賺錢的好時(shí)機(jī),不斷給你施加壓力,要求提前到9月20日完工。你應(yīng)該如何行動(dòng)?()查看答案
試題參考答案:A
試題5
scrum團(tuán)隊(duì)的成員經(jīng)常與另一個(gè)使用看板的團(tuán)隊(duì)產(chǎn)生誤解。兩個(gè)團(tuán)隊(duì)?wèi)?yīng)該如何做?查看答案
試題參考答案:D
試題6
新項(xiàng)目經(jīng)理意識(shí)到項(xiàng)目團(tuán)隊(duì)和項(xiàng)目相關(guān)方不清楚項(xiàng)目狀態(tài),項(xiàng)目經(jīng)理感到困查看答案
試題參考答案:B
試題7
項(xiàng)目經(jīng)理被任命管理一個(gè)改造項(xiàng)目。在安裝期間出現(xiàn)一個(gè)安裝缺陷,需要技術(shù)資源修復(fù)。項(xiàng)目經(jīng)理通過哪份文件將這種情況與相關(guān)方溝通?查看答案
試題參考答案:C
試題8
項(xiàng)目經(jīng)理帶領(lǐng)20名團(tuán)隊(duì)成員執(zhí)行一個(gè)項(xiàng)目,客戶終止了項(xiàng)目并選擇與其他供應(yīng)商合作。項(xiàng)目經(jīng)理接下來應(yīng)執(zhí)行下列哪項(xiàng)?查看答案
試題參考答案:C
試題9
A project manager leading an inexperienced project team identifies that business requirements document may not be completed on time.Since this could impact the start of the next activity the project manager arranges for extra resources to reduce the uncertainty.What should the project manager do next?查看答案
試題參考答案:B
試題10
A new project manager assigned to an ongoing project discovers that the cost performance index is 0.75,and the schedule is two weeks delayed. What should the project manager do to recover the schedule delay?查看答案
試題參考答案:C
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |