Two project managers have just realized that they are in a weak matrix organization and that their power as project managers is quite limited. One figures out that he is really a project expediter and the other realizes he is really a project coordinator. How is a project expediter different from a project coordinator?
A、The project expediter cannot make decisions.
B、The project expediter can make more decisions.
C、The project expediter reports to a higher-level manager.
D、The project expediter has some authority.