信息系統(tǒng)項目管理師每日一練試題內(nèi)容(2018/5/23)
試題1: 項目配置管理的主要任務(wù)中,不包括( )。
A.版本管理
B .發(fā)行管理
C .檢測配置
D .變更控制
完成活動A所需的時間,悲觀(P)的估計需36天,最可能(ML)的估計需21天,樂觀(O)的估計需6天?;顒覣在16天至26天內(nèi)完成的概率是( )。
A. 55.70%
B. 68.26%
C. 95.43%
D. 99.73%
The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).
(1)A. waterfall model
B. workflow reference model
C. evolutionary model
D. spiral model
(2)A. workflow engines
B. processes
C. workflow threads
D. tasks
( )不是超安全的信息安全保障系統(tǒng)(S2-MIS)的特點或要求。
A.硬件和系統(tǒng)軟件通用
B.PKI/CA安全保障系統(tǒng)必須帶密碼
C.業(yè)務(wù)應(yīng)用系統(tǒng) 在實施過程中有重大變化
D.主要的硬件和系統(tǒng)軟件需要PKI/CA認(rèn)證
范圍控制的目的是監(jiān)控項目的狀態(tài),如“項目的工作范圍狀態(tài)和產(chǎn)品范圍狀態(tài)”,范圍控制不涉及( )。
A.影響導(dǎo)致范圍變更的因素
B.確保所有被請求的變更按照項目整體變更控制過程處理
C.范圍變更發(fā)生時管理實際的變更
D.確定范圍變更是否已經(jīng)發(fā)生
某單位計劃開發(fā)信息系統(tǒng)來實現(xiàn)其全員工資計算的自動化,根據(jù)《軟件文檔管理指南GB/T16680-1996》,該信息系統(tǒng)項目中的文檔質(zhì)量等級最低應(yīng)達(dá)到( )。
A.4級
B.3級
C.2級
D.1級
公司要求項目團(tuán)隊中的成員能夠清晰地看到與自己相關(guān)的所有活動以及和某個活動相關(guān)的所有成員。項目經(jīng)理在編制該項目人力資源計劃時應(yīng)該選用的組織結(jié)構(gòu)圖類型是( )。
A.層次結(jié)構(gòu)圖
B.矩陣圖
C.樹形圖
D.文本格式描述
()是指企業(yè)與政府機構(gòu)之間進(jìn)行電子商務(wù)活動
A、B2A
B、B2B
C、B2C
D、C2A
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |