信息系統(tǒng)項(xiàng)目管理師考試英語練習(xí)題(十)
1、During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised ( )are necessary.
A. proceedings
B. controls
C. forecasting’s
D. prelibations
信管網(wǎng)解析
參考譯文:在項(xiàng)目過程中,由于各種原因,需求會發(fā)生變化。隨著需求的變化和工作的進(jìn)行,會產(chǎn)生額外的需求,可能需要對現(xiàn)有需求進(jìn)行更改。必須有效地管理這些添加和更改。為了有效地分析變更的影響,有必要知道每個(gè)需求的來源,并記錄任何變更的理由。然而,項(xiàng)目經(jīng)理可能希望跟蹤需求波動性的適當(dāng)度量,以判斷是否需要新的或修訂的控制。
信管網(wǎng)參考答案:B
2、Project Quality Management processes include all the activities of the ( ) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A. project
B. project management team
C. performing organization
D. customer
信管網(wǎng)解析:
參考譯文:項(xiàng)目質(zhì)量管理過程包括執(zhí)行組織確定質(zhì)量方針、目標(biāo)和責(zé)任的所有活動,以使項(xiàng)目滿足其所承擔(dān)的需求。
信管網(wǎng)參考答案:C
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |