During project closure a project sponsor complains that the project did not increase the department’s knowledge of Java programming and therefore, the project is not complete. The customer has accepted the project. The project manager determines that all stated objective and deliverables have been met. He does not find evidence that Java programming was an objective .A review of project correspondence shows no mention of the deliverable. The project manager should:
A、close project
B、re-plan the project to include the new objective
C、meet with the team to discuss the issue and find a resolution
D、get the project stakeholders involved to help resolve the issue
我的答案與分析 查看全部答題與分析 | |
|
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。