信息系統(tǒng)項目管理師當天每日一練試題地址:m.xiexiliangjiufa.com/exam/ExamDay.aspx
往期信息系統(tǒng)項目管理師每日一練試題匯總:m.xiexiliangjiufa.com/class/27/e1_1.html
信息系統(tǒng)項目管理師每日一練試題(2021/4/16)在線測試:m.xiexiliangjiufa.com/exam/ExamDay.aspx?day=2021/4/16
信息系統(tǒng)項目管理師每日一練試題內容(2021/4/16)
試題1: 某公司準備將運行在本地局域網(wǎng)上的CRM系統(tǒng)遷移到集團云平臺上并做適當?shù)墓δ軘U充,從信息系統(tǒng)生命周期的角度看,該CRM系統(tǒng)處于( )階段。
A、立項
B、開發(fā)
C、運維
D、消亡
在制定項目質量計劃中,()運用統(tǒng)計方法幫助項目確定影響特定變量的因素,經(jīng)常用于項目產(chǎn)品的分析。
A.基準比較
B.質量成本分析
C.流程圖
D.實驗設計
The project life-cycle can be described as( ).
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
The strategies for handling risk comprise of two main types:negative risks, and positive risks.The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies( ),Transfer ,Mitigate .
A.Challenge
B.Exploit
C.Avoid
D.Enhance
如下圖所示,某公司局域網(wǎng)防火墻由包過濾路由器R 和應用網(wǎng)關F 組成,下面描述錯誤的是( )。
A.可以限制計算機C 只能訪問Internet 上在TCP 端口80 上開放的服務
B.可以限制計算機A 僅能訪問以"202"為前綴的IP 地址
C.可以使計算機B 無法使用FTP 協(xié)議從Internet 上下載數(shù)據(jù)
D.計算機A 能夠與計算機X 建立直接的TCP 連接
某項目各期的現(xiàn)金流量如下表所示:
設貼現(xiàn)率為10%,則項目的凈現(xiàn)值約為( )。
A.140
B.70
C.34
D.6
以下各項中,( )不是整體變更控制的輸入。
A.已批準的糾正措施
B.工作績效報告
C.變更請求
D.項目管理計劃
項目承建方在立項管理過程中,應從多個角度對項目進行論證,以下通常不屬于承建方項目論證內容的是( )。
A.技術可行性分析
B.財務可行性分析
C.風險分析
D.需求驗證
溫馨提示:因考試政策、內容不斷變化與調整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |