69題: Since risk is associated with most projects, the best course of act is to()。
A、cover all project risks by buying appropriate insurance
B、ignore the risks ,since nothing can be done about them and move forward with the project in an expeditious manner
C、avoid projects with clear and present risk
D、identify various risks and implement actions to mitigate the potential impact
答案解析與討論:
m.xiexiliangjiufa.com/st/1284819172.html第
70題: OSPF routing protocol typically runs over()。
A、IP
B、TCP
C、UDP
D、ARP
答案解析與討論:
m.xiexiliangjiufa.com/st/1284910538.html第
71題:
cost of quality is ()
A.primarily coused by poor workmanship of workers who are building or manufacturing the produce
B.associated with non-conformence to specifications and requirements
C.used to determine whether a quality management program is suitable for a given project
D.negligible for most large projects
答案解析與討論:
m.xiexiliangjiufa.com/st/1285016398.html第
73題: With a clear SOW a contractor completes work as specified,but the buyer not pleased with the result.The contract is considered to be()。
A、incomplete because the buyer is not pleased
B、incomplete because the specs are incorrect
C、complete because the contractor is satisfied
D、complete because the contractor meets the terms and conditions of the contract
答案解析與討論: