當前位置:信管網 >> 在線考試中心 >> 信息系統項目管理師題庫 >> 試題查看
試卷名稱 信息系統項目管理師-pmp練習題-1
考試中心《信息系統項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A project manager is working on a project to launch a new internet service. The project manager plans that this work is to be done by the support team. The support team does not want to do the work because they do not have the necessary expertise and claim that they have never heard of the project. What is the root cause of this problem ?
A、Communication plan was not used.
B、Project manager did not involve all the stakeholders.
C、Support team is not prepared to do the task.
D、Project manager did not identify the risk about the lack of professional knowledge.