女人久久久www免费人成看片,国内自拍偷拍网,国产一区二区三区免费在线观看,欧美精品三区四区,91久久国产综合久久91,欧美成人精品第一区二区三区 ,美女成人在线观看

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The asphalt highway project that the project manager is managing is 50% complete. The PM planned on having 4,000 square yards of asphalt placed by now, but in actuality. They’ve finished placing 8,000 square yards. The estimated cost forth is work was $ 1 per square yard. The actual cost for this work is $ 8,000.What does this tell the project manager?
A、EV is 2.
B、SPI is 2.
C、SPI is 0.50.
D、SV is 0.50


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容