70題: 某項目有4個硬件的生產(chǎn)任務(wù)需要完成,有4個硬件廠商可選擇,每個廠商只能分配一個任務(wù)。下表是各廠商完成各硬件生產(chǎn)所需的時間:

則4個硬件生產(chǎn)完成的總時間最短為()
A.25
B.26
C.27
D.28
答案解析與討論:
m.xiexiliangjiufa.com/st/6330625892.html第
71題: ()usesthedataandresultsfromthe()processtoreflecttheoverallqualitystatusoftheprojecttothestakeholders.
A.ControlQuality;planqualitymanagement
B.PlanQualityManagement;managequality
C.ManageQuality;controlquality
D.ControlQuality;managequality
答案解析與討論:
m.xiexiliangjiufa.com/st/6330724148.html第
72題: How frequently the risks are being reviewed ,this should recorded in( ).
A.Risk Management Plan
B.Issue Log
C.Risk Register
D.Risk Report
答案解析與討論:
m.xiexiliangjiufa.com/st/6330825426.html第
74題: ()istheprocessofspecifyingtheapproachandidentifyingpotentialsellers.
A.PlanProcurementManagement
B.CloseProcurementManagement
C.ControlProcurement
D.ConductProcurement
答案解析與討論:
m.xiexiliangjiufa.com/st/6331026083.html第
75題: The project manager should use()tool for the purpose toreporton the work remaining for projects.
A.cumulative flow diagram
B.burndown chart
C.forecast estimation
D.earned value
答案解析與討論: