Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.
A.a(chǎn)ctivity duration estimating, schedule developing, activity resource estimating
B .a(chǎn)ctivity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.a(chǎn)ctivity resource estimating, schedule developing, activity duration estimating
某項(xiàng)目投資額為190 萬(wàn)元,實(shí)施后的利潤(rùn)分析如下表所示:
假設(shè)貼現(xiàn)率為0.1,則項(xiàng)目的投資收益率為( )。
A.0.34
B.0.41
C.0.58
D.0.67
甲乙丙為三個(gè)獨(dú)立項(xiàng)目,NPV 甲=12 萬(wàn)元,NPV 乙=15 萬(wàn)元,NPV 丙=18 萬(wàn)元,三個(gè)項(xiàng)目的初始投資額相同,并且回收期相同,則應(yīng)優(yōu)先選擇( )項(xiàng)目進(jìn)行投資。
A.甲
B.乙
C.丙
D.甲或乙
某項(xiàng)目各期的現(xiàn)金流量如下表所示:
設(shè)貼現(xiàn)率為10%,則項(xiàng)目的凈現(xiàn)值約為( )。
A.140
B.70
C.34
D.6
Many useful tools and techniques are used in developing schedule.( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain method
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by ( ).
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.( ) is not a project configuration management tool.
A.Rational Clearcase
B.Quality Function Deployment
C.Visual SourceSafe
D.Concurrent Versions System