24題: 某項目經理在估算某軟件開發(fā)活動的成本時,發(fā)現該項目模塊與歷史項目高度相似,但當前項目要求引入AT技術,導致分開發(fā)工作量增加10%。項目經理參考了歷史項目的功能點成本數據,并結合AI技術的復雜度系數進行調整,最終得出活動成本估算值。項目經理主要使用了以下哪種技術()。
A.三點估算
B.類比估算
C.參數估算
D.儲備分析答案解析與討論:
m.xiexiliangjiufa.com/st/7821828834.html第
25題: 監(jiān)督溝通過程的輸入不包含()。
A.已開展的溝通的信息
B.計劃溝通的實際開展情況
C.關于已開展的溝通類型和數量的數據
D.項目早期的經驗教訓答案解析與討論:
m.xiexiliangjiufa.com/st/7821928834.html第
26題: () is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.
A. Plan risk responses
B. Plan risk management
C. Implement risk responses
D. Perform quantitative risk analysis答案解析與討論:
m.xiexiliangjiufa.com/st/7822028834.html第
53題: When using earned value analysis, the( )is compared to actual results to determine if a change, corrective action, or preventive action is necessary.
A. cost baseline
B. performance measurement baseline
C. schedule baseline
D. scope baseline
答案解析與討論:
m.xiexiliangjiufa.com/st/782349290.html第
54題: 監(jiān)督是貫穿于整個項目的項目管理活動之一,包括收集、測量和( ),以及預測趨勢,以便推動( )。
A 分析收集數據 數據分析
B.分析測量結果 過程改進
C.評估項目績效 績效優(yōu)化
D.檢查項目風險 風險管理
答案解析與討論:
m.xiexiliangjiufa.com/st/782355046.html第
55題: 某醫(yī)療器械公司正在研發(fā)一款新型的醫(yī)療診斷設備,該設備需要符合嚴格的國家和國際醫(yī)療設備標準。但相關法規(guī)和標準不斷更新,如果等產品開發(fā)完成后再進行合規(guī)性測試,可能會導致產品不符合最新的法規(guī)要求,無法通過干系人的驗收,該項目適合采用( )的開發(fā)方法,項目經理需要具有( )領導風格。
A. 適應型 服務型
B. 適應型 指導型
C. 預測型 變革型
D. 預測型 權威型
答案解析與討論: