高頻錯題(8)
1、 [單選] 一個項目接近完工,這時項目經(jīng)理發(fā)現(xiàn)一個新風(fēng)險。發(fā)現(xiàn)這個風(fēng)險時,項目經(jīng)理執(zhí)行的是什么活動?
A project is nearing completion when the project manager discovers a new risk. What activity was the project manager performing when they discovered this risk?
A:識別風(fēng)險
Identifying risks
B:定量風(fēng)險分析
Quantitative risk analysis
C:風(fēng)險再評估
Risk reassessment
D:監(jiān)督風(fēng)險
Controlling risks
正確答案:C 你的答案:D
解析:在監(jiān)督風(fēng)險中,經(jīng)常需要識別新風(fēng)險,對現(xiàn)有風(fēng)險進(jìn)行再評估,以及刪去已過時的風(fēng)險。 應(yīng)該定期進(jìn)行項目風(fēng)險再評估。反復(fù)進(jìn)行再評估的次數(shù)和詳細(xì)程度,應(yīng)該根據(jù)相對于項目目標(biāo)的項目進(jìn)展情況而定。
2、 [單選] 在項目初始階段,項目發(fā)起人表示項目必須在六個月內(nèi)完成。若要確定時間線是否切合實際,項目經(jīng)理應(yīng)該怎么做?
During a project’s initial phase, the project sponsor expresses that it must be completed within six months. What should the project manager do to determine if the timeline is realistic?
A:咨詢主題專家(SME)。
Consult subject matter experts (SMEs).
B:查看資源管理計劃。
Refer to the human resource management plan.
C:查看進(jìn)度管理計劃。
Refer to the schedule management plan.
D:安排一次與項目相關(guān)方召開的焦點小組會議。
Arrange a focus group with project stakeholders.
正確答案:D 你的答案:A
解析:若要確定時間線是否切合實際,需要具體執(zhí)行工作的團隊成員參與評估,因此安排一次與項目相關(guān)方召開的焦點小組會議比較合適。
3、 [單選] 作為一個大型組織中關(guān)鍵項目的組成部分,部門制造業(yè)務(wù)被外包給第三方,項目經(jīng)理得知部門自己來執(zhí)行將比預(yù)期更早到達(dá)且數(shù)量更多,項目經(jīng)理下一步應(yīng)該怎么做?
As part of a key project in a large organization, the department's manufacturing business was outsourced to a third party. The project manager learned that the department's execution would arrive earlier than expected and the number was greater. What should the project manager do next?
A:審查項目進(jìn)度計劃并快速跟進(jìn)活動,以便盡早完成項目
Review the project schedule and fast track activities to complete the project as soon as possible
B:增加額外資源,盡早結(jié)束項目,并更新經(jīng)驗教訓(xùn)
Increase additional resources to complete the project as soon as possible and update lessons learned
C:審查采購管理計劃來審查第三方的交付條款
Review the procurement management plan to review the delivery terms of the third party
D:審查成本和進(jìn)度計劃
Review costs and schedule
正確答案:D 你的答案:C
解析:首先需要審查外包行為是否可以滿足成本和進(jìn)度計劃,如果不行,再做變更,如果可以滿足項目需求,再收集其他信息決定是否要變更
4、 [單選] 在項目執(zhí)行過程中,一位相關(guān)方要求一名團隊成員執(zhí)行與項目無關(guān)的緊急任務(wù),團隊成員執(zhí)行了該請求,導(dǎo)致其項目相關(guān)活動延后,項目經(jīng)理在一次狀態(tài)報告會上得知這一情況,項目經(jīng)理應(yīng)該怎么做?
In the execution of the project, a stakeholder required a team member to perform emergency tasks that were unrelated to the project. The team member executed the request, resulting in delays in project-related activities. The project manager learned this at a status report meeting. What should the project manager do?
A:要求該團隊成員加班去彌補損失的時間
Ask the team member to work overtime to make up for the loss
B:通知相關(guān)方預(yù)期交付期限無法滿足
Notify the stakeholder that the expected delivery deadline cannot be met
C:強調(diào)遵循溝通管理計劃的重要性
Emphasize the importance of following the communication management plan
D:建議重新規(guī)劃項目活動
Recommend to re-plan project activities
正確答案:D 你的答案:C
解析:其相關(guān)活動延后的情況已經(jīng)發(fā)生,目前能做的只是重新規(guī)劃項目活動,力爭按時交付項目。
5、 [單選] 一個項目延遲交付,且需要進(jìn)行變更才能獲得理想的可交付成果質(zhì)量級別,項目經(jīng)理提出一個正式的變更請求,并與所有相關(guān)方溝通變更,然后項目經(jīng)理得知這種溝通方式未能滿足相關(guān)方期望,項目經(jīng)理應(yīng)該怎么做?
A project has been delayed in delivery and needs to be changed to achieve the desired quality level of deliverables. The project manager made a formal change request and communicated the changes with all stakeholders. Then the project manager learned that this communication method failed to meet stakeholders' expectations. What should the project manager do?
A:審查溝通管理計劃和相關(guān)方參與計劃
Review communication management plan and stakeholder management plan
B:簽發(fā)變更要求,在項目管理計劃中包含相關(guān)方的期望
Issue a change request and include stakeholders' expectations in the project management plan
C:與項目發(fā)起人開會,以更好地了解相關(guān)方的期望
Meet with project sponsor to better understand stakeholders' expectations
D:遵循溝通管理計劃,并簽發(fā)一份狀態(tài)報告
Follow the communication management plan and issue a status report
正確答案:A 你的答案:B
解析:考點:10.3 監(jiān)督溝通。首先得明確,本題考的是溝通效果不好怎么做,前面項目狀態(tài)和變更部分的描述都是背景材料,也是干擾項,首先排除。然后,題眼是溝通方式未能滿足相關(guān)方期望,這里的溝通方式默認(rèn)是按照溝通管理計劃中制定的方式實施。在監(jiān)督溝通的過程中,發(fā)現(xiàn)溝通失效或效果不好,首先應(yīng)審核溝通管理計劃和相關(guān)方參與計劃,然后確定是否需要更新這些計劃,選A。
6、 [單選] 新任命的項目經(jīng)理獲悉,相關(guān)方對已識別的項目問題和風(fēng)險非常擔(dān)心,他們對超過一個月時間里沒有任何溝通表示不滿。新項目經(jīng)理應(yīng)該怎么做?
The newly appointed project manager was informed that the stakeholders were very worried about the identified project issues and risks. They were dissatisfied with no communication for more than a month. What should the new project manager do?
A:實施現(xiàn)有溝通管理計劃和相關(guān)方參與計劃
Implement the existing communication management plan and stakeholder management plan
B:更新現(xiàn)有溝通管理計劃和相關(guān)方參與計劃,并立即向相關(guān)方提供有關(guān)問題和風(fēng)險
Update the existing communication management plan and stakeholder management plan and immediately provide stakeholders with relevant issues and risks
C:與相關(guān)方開會以確定溝通所需的頻率,然后立即向他們提供有關(guān)這些問題和風(fēng)險
Meet with stakeholders to determine the frequency of communication needed, and then immediately provide them with these issues and risks
D:與關(guān)鍵相關(guān)方開會,然后更新溝通管理計劃和相關(guān)方參與計劃
Meet with key stakeholders and then update the communication management plan and stakeholder management plan
正確答案:D 你的答案:C
解析:考點:10.3 監(jiān)督溝通。本題考的仍舊是溝通不好怎么辦的問題。按照流程,先分析原因,然后通過整體變更控制程序,最后實施變更。D選項先與關(guān)鍵相關(guān)方開會尋找原因,然后變更計劃,正確。A選項直接實施現(xiàn)有效果不好的計劃,錯誤。B選項立即更新計劃,錯誤。C選項未涉及溝通計劃,錯誤。
————————————————