試題1
建議項(xiàng)目采用一項(xiàng)新技術(shù),但擁有這項(xiàng)技術(shù)的唯一一家供應(yīng)商身處另一個國家,項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:D
試題2
A global project has several undefined conditions. To understand the impact of the assumptions.and to plan the mitigation of the uncertainties, what technique should the project manager use?()查看答案
試題參考答案:A
試題3
一位項(xiàng)目團(tuán)隊(duì)成員已經(jīng)延遲兩次交付一個工作包,其職能經(jīng)理已經(jīng)通知項(xiàng)目經(jīng)理,該團(tuán)隊(duì)成員相對較新,需要時間學(xué)習(xí)。項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題4
對已經(jīng)完成的工作,項(xiàng)目經(jīng)理要求實(shí)施嚴(yán)格的質(zhì)是控制措施,保證錯誤不落在客戶手中。這種做法可以()。查看答案
試題參考答案:B
試題5
The customer requests a change to the project that would increase the project risk. Which of the following should you do before all the others?()查看答案
試題參考答案:C
試題6
A project is completed and customer approval is obtained.Th e IT department plans an unscheduled audit of the project. W hat should the project manager do查看答案
試題參考答案:B
試題7
項(xiàng)目經(jīng)理計(jì)算出當(dāng)前PV=10000美元,AC=12000美元,S PI=1.3。項(xiàng)目經(jīng)理由此計(jì)算CPI,下列說法正確的是∶查看答案
試題參考答案:D
試題8
與項(xiàng)目團(tuán)隊(duì)一起,項(xiàng)目經(jīng)理發(fā)現(xiàn)了可以實(shí)施快速跟進(jìn)的兩項(xiàng)工作,即在任務(wù)A開始1天后就開始實(shí)施任務(wù)C,從而使任務(wù)C與任務(wù)A并行實(shí)施3天。這種做法對項(xiàng)目完工日期有什么影響?()查看答案
試題參考答案:D
試題9
During a project's user acceptance stage,some user's comp lain that their expectations have not been met. What should t he project manager have done differently?查看答案
試題參考答案:A
試題10
Although the stakeholders thought there was enough money in the budget., halfway through the project the cost performance index(CPI)is 0.7. To determine the root cause,several stakeholders audit the project and discover the project cost budget was estimated analogously.Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was completed. Which of the following describes what was missing?查看答案
試題參考答案:C
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |