PMP?每日一練試題內(nèi)容(2022/7/10)
試題1
作為一個(gè)項(xiàng)目經(jīng)理,你在制定一份文檔以描述項(xiàng)目可交付成果為滿足合同、標(biāo)準(zhǔn)、規(guī)格或其它正式強(qiáng)制性文件的要求,而應(yīng)具備的特征或性能。這份文檔也稱作∶查看答案
試題參考答案:A
試題2
變更控制委員會(huì)批準(zhǔn)了對(duì)項(xiàng)目進(jìn)度基準(zhǔn)的變更。由于項(xiàng)目的可交付成果將作為公司的新產(chǎn)品上市,運(yùn)營(yíng)經(jīng)理表示不滿,懷疑對(duì)該變更的審查和批準(zhǔn)存在漏洞。你將如何證明該變更是符合正式流程的? ()查看答案
試題參考答案:D
試題3
A project manager is notified that a software developer for a critical section of code will be out of the office for three wee ks. This task is not part of the critical path. What should the project manager do next?查看答案
試題參考答案:B
試題4
You are asked to produce a 10-meterlong tube, and you are producing tubes within the range of 12.1 m,11.98 m,12.12 m, 12.08, etc. This means that:查看答案
試題參考答案:B
試題5
項(xiàng)目在落后于進(jìn)度一個(gè)月的情況下完成.項(xiàng)目經(jīng)理需要立即獲得客戶的最終驗(yàn)收,最終驗(yàn)收標(biāo)準(zhǔn)中應(yīng)包含哪些內(nèi)容?查看答案
試題參考答案:B
試題6
For a process review, a laboratory uses Lean Six Sigma methodology. Mid-way through the project, an audit is scheduled with an external Lean consultant to ensure that the methodology is applied appropriately. What is this process called?查看答案
試題參考答案:D
試題7
A project manager informs the sponsor that the project is behind schedule. The project sponsor threatens to cancel the project as the sponsor does not want to miss the target completion date. Which of the following techniques should the project manager us to expedite the project?查看答案
試題參考答案:C
試題8
在一個(gè)為期三年的項(xiàng)目中途,任命了一名新項(xiàng)目經(jīng)理。在第一次團(tuán)隊(duì)會(huì)議上,新項(xiàng)目經(jīng)理得知有關(guān)洪水的情況,以及洪水可能摧毀設(shè)備的風(fēng)險(xiǎn)。項(xiàng)目經(jīng)理首先應(yīng)該做什么?查看答案
試題參考答案:C
試題9
What will the project manager need to consider in preparing a coherent risk management plan?查看答案
試題參考答案:B
試題10
The project has been going relatively well,although there have been some problems with resource availability and the project scope has changed more than was expected. The project is now completing one of its phase.Of all decisions the sponsor must consider during an end-of-phase review meeting,the MOST difficult is:查看答案
試題參考答案:C
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。