The stakeholder is requesting a major change to the project scope. The change is of vital importance to the stakeholders. The project manager performs the necessary analysis of the large and finds that, because of the impact on project cost and schedule, it needs to go through the Changes Control Board(CCB). The CCB denies the change. What should the project manager do next?
A、Implement the change despite the decision made by CCB, because the change is vital to the stakeholder and to the success of the project.
B、 Include the decision from the CCB in the change log, notify the stakeholders and the team of the situation.
C、 Recommend immediately that the project be stopped and new requirements gathering should be performed.
D、 Meet with the CCB members individually to influence them to change their decision.
我的答案與分析 查看全部答題與分析 | |
|
溫馨提示:因考試政策、內容不斷變化與調整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。