1、 Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( )
A. project management plan
B. project baseline
C. risk response plan
D. risk baseline
信管網(wǎng)參考答案:A
在項(xiàng)目計(jì)劃過(guò)程中,風(fēng)險(xiǎn)管理和記錄是非常重要的。您正在定義關(guān)鍵風(fēng)險(xiǎn),包括約束和假設(shè),以及計(jì)劃的響應(yīng)和意外事件。這些詳細(xì)信息將包含在()
A、 項(xiàng)目管理計(jì)劃
B、 項(xiàng)目基線
C、 風(fēng)險(xiǎn)應(yīng)對(duì)計(jì)劃
D、 風(fēng)險(xiǎn)基線
查看解析:http://m.xiexiliangjiufa.com/st/2879.html
2、 The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. ( )could provide the fund to cover the newly discovered work item.
A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund
信管網(wǎng)參考答案:C
項(xiàng)目預(yù)算已經(jīng)定稿。附加發(fā)現(xiàn)預(yù)算或項(xiàng)目范圍內(nèi)沒(méi)有計(jì)劃的工作。()可以為新發(fā)現(xiàn)的工作項(xiàng)目提供資金。
A、 應(yīng)急準(zhǔn)備金
B、 項(xiàng)目利潤(rùn)
C、 管理準(zhǔn)備金
D、 專項(xiàng)基金
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |