PDM includes four types of dependencies or precedence relationships…( ). The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-Start B.Finish-to-FinishC.Start-to-Start D.Start-to-Finish
信管網(wǎng)參考答案:D(僅供參考,歡迎評論交流) 收藏