If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and(  ) of the project management plan. Are revised and reissued to reflect the approved changes
	A、developing baselines
	B、testing baselines
	C、schedule baselines
	D、ending baselines