第
72題: Generally, the contract claim can be settled amicably through negotiation. If no compromise can be reached, the dispute can be settled by ( ).
A. negotiation
B. the court
C. lawyer
D. arbitration
答案解析與討論:
m.xiexiliangjiufa.com/st/4056723685.html第
73題: The organization shall undertake change in a planned and systematic manner, taking account of the review of the potential consequences of changes and taking action as necessary, to ensure the integrity of goods and services are maintained. This is called ( ).
A. control of changes
B. control of plans
C. control of accounts
D. control of service
答案解析與討論:
m.xiexiliangjiufa.com/st/4056822894.html第
74題: Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control is the management of the approved ( ).
A. schedule baseline
B. cost baseline
C. cost output
D. cost input
答案解析與討論:
m.xiexiliangjiufa.com/st/4056914819.html