70題: 某系統(tǒng)集成企業(yè)在項目實施階段出現(xiàn)突發(fā)情況,引起進度問題。此時監(jiān)理單位應(yīng)通過( ),督促各方采取應(yīng)急措施趕上進度要求,以便項目的開發(fā)能以預(yù)期進度完成。
A.監(jiān)理日報
B.監(jiān)理周報
C.監(jiān)理月報
D.監(jiān)理專題會議
答案解析與討論:
m.xiexiliangjiufa.com/st/405657128.html第
71題: ( )techniques are used to find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work .
A. Schedule forecasts
B. Schedule compression
C. Change requests
D. Data analysis
答案解析與討論:
m.xiexiliangjiufa.com/st/4056616420.html第
72題: Generally, the contract claim can be settled amicably through negotiation. If no compromise can be reached, the dispute can be settled by ( ).
A. negotiation
B. the court
C. lawyer
D. arbitration
答案解析與討論:
m.xiexiliangjiufa.com/st/4056723685.html第
74題: Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control is the management of the approved ( ).
A. schedule baseline
B. cost baseline
C. cost output
D. cost input
答案解析與討論:
m.xiexiliangjiufa.com/st/4056914819.html第
75題: The top management of a company will review the organization’s management system, the management review will include consideration of :
( a ) customer feedback on quality
( b ) processes performance and product conformity
The purpose of management review is ( ).
A
. control of customers
B. control of measurements
C. control of qualities
D. control of opportunities
答案解析與討論:
m.xiexiliangjiufa.com/st/4057018688.html