第
72題: ()is not the application scenario of artificial intelligence.
A.a(chǎn)utonomous robot
B.face recognition
C.self-driving
D.conditioned reflex
答案解析與討論:
m.xiexiliangjiufa.com/st/5382518863.html第
73題: This ()is the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed.
A.a(chǎn)ctivity
B.planning package
C.work package
D.requirement
答案解析與討論:
m.xiexiliangjiufa.com/st/5382611557.html第
74題: Monitor Risk is not the process of () throughout the project.
A.monitoring the implementation of agree-upon risk response plans
B.Prioritizing individual project risks
C.Tracking and identifying new risks
D.Evaluating risk effectiveness
答案解析與討論:
m.xiexiliangjiufa.com/st/5382715257.html