試題1
根據(jù)項(xiàng)目預(yù)測(cè),項(xiàng)目結(jié)束時(shí)將會(huì)超出預(yù)算。你應(yīng)該首先考慮下列哪個(gè)方案?()查看答案
試題參考答案:D
試題2
你的項(xiàng)目團(tuán)隊(duì)中有兩名成員在過(guò)去幾周的時(shí)間里一直在爭(zhēng)論對(duì)于這個(gè)項(xiàng)目來(lái)說(shuō)哪個(gè)項(xiàng)目管理軟件最有效的問(wèn)題,你已經(jīng)對(duì)他們的爭(zhēng)論感到厭煩。因此,你決定要召集一次會(huì)議,借機(jī)看看他們能否在意見(jiàn)上求同存異,進(jìn)而解決方案努力,并最終達(dá)成共識(shí)。你將會(huì)使用下列哪種類(lèi)型的爭(zhēng)端解決辦法?查看答案
試題參考答案:B
試題3
項(xiàng)目團(tuán)隊(duì)人成員位干不同時(shí)區(qū)。在這種情況下,下列哪項(xiàng)對(duì)項(xiàng)目成果非常重要?查看答案
試題參考答案:A
試題4
一個(gè)最近實(shí)施項(xiàng)目的客戶(hù)要求項(xiàng)目經(jīng)理調(diào)查項(xiàng)目交付后業(yè)務(wù)中斷和損失的問(wèn)題。項(xiàng)目經(jīng)理向客戶(hù)解釋該請(qǐng)求必須轉(zhuǎn)給運(yùn)營(yíng)團(tuán)隊(duì),因?yàn)轫?xiàng)目已正式驗(yàn)收。客戶(hù)不同意并且進(jìn)行了投訴。項(xiàng)目經(jīng)理應(yīng)進(jìn)行下列哪項(xiàng)?查看答案
試題參考答案:B
試題5
高層領(lǐng)導(dǎo)批準(zhǔn)了一個(gè)戰(zhàn)略項(xiàng)目,項(xiàng)目團(tuán)隊(duì)估算了開(kāi)發(fā)產(chǎn)品所需的時(shí)間。隨后,項(xiàng)目部分團(tuán)隊(duì)成員離開(kāi)公司,一些新的成員補(bǔ)充入團(tuán)隊(duì),在成本估算時(shí),項(xiàng)目經(jīng)理應(yīng)考慮哪些因素?查看答案
試題參考答案:A
試題6
某項(xiàng)目經(jīng)理受命承擔(dān)一個(gè)項(xiàng)目,并且目前通過(guò)團(tuán)體活動(dòng)制定該項(xiàng)目的需求基線(xiàn)。可采用何種團(tuán)體活動(dòng)方法?查看答案
試題參考答案:B
試題7
你負(fù)責(zé)的當(dāng)前項(xiàng)目快結(jié)束了,幾個(gè)新出現(xiàn)的項(xiàng)目相關(guān)方得知該項(xiàng)目會(huì)對(duì)他們?cè)斐捎绊懀吞岢隽艘恍╊~外的需求。由此產(chǎn)生了問(wèn)題,因?yàn)槟愕捻?xiàng)目管理計(jì)劃并未包括實(shí)現(xiàn)額外需求所需的資金和時(shí)間。為了避免類(lèi)似問(wèn)題出現(xiàn)在未來(lái)的項(xiàng)目中,你最應(yīng)該做什么? ()查看答案
試題參考答案:D
試題8
若要實(shí)施來(lái)自外部審計(jì)的建議,項(xiàng)目經(jīng)理應(yīng)該做什么?查看答案
試題參考答案:C
試題9
An organization is awarded a large construction project.The project team is implementing an approach to continuously optimize execution efficiency. What approach should the projec t team use a basis for improvement ?查看答案
試題參考答案:B
試題10
A project manager presents the project charter to the steering committee.The steering committee is concerned about preassigned resource allocation because the stakeholders are unaware of their participation in the project. What should the project manager have done to avoid this?查看答案
試題參考答案:C
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專(zhuān)業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專(zhuān)業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿(mǎn)足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |