試題1
識別風險應該由哪些人進行:查看答案
試題參考答案:D
試題2
以下哪個是分析問題的工具?查看答案
試題參考答案:C
試題3
項目資源理的主要過程是:查看答案
試題參考答案:D
試題4
Negotiations between two parties are becoming complex,so party buyer makes some notes that both parties sign. However, when the work s being done.party seller claims that they are not required to provide an item they both agreed to during negotiations, because it was not included in the subsequent contract, in this case, party seller is:查看答案
試題參考答案:D
試題5
已經宣布發(fā)布新產品,但在驗收測試期間,識別到幾個缺陷,項目經理應該怎么做?查看答案
試題參考答案:C
試題6
生產經理指出,工程團隊主管未考慮他們的請求,由于他們都是項目團隊成員,這種情況也導致項目延期。項目經理應該怎么做?查看答案
試題參考答案:B
試題7
評估項目需求之后,項目經理決定招幕一名主題專家,而該主題專家將采用虛擬方式工作。為制訂項目溝通計劃,項目經理應該怎么做?查看答案
試題參考答案:B
試題8
對每個功能的商業(yè)價值,由誰來負責定義?查看答案
試題參考答案:A
試題9
Although the stakeholders thought there was enough money in the budget., halfway through the project the cost performance index(CPI)is 0.7. To determine the root cause,several stakeholders audit the project and discover the project cost budget was estimated analogously.Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was completed. Which of the following describes what was missing?查看答案
試題參考答案:C
試題10
客戶拒收團隊開發(fā)的一個Web應用程序,因為客戶認為需求被遺漏。為確保開發(fā)的工作通過驗收,團隊應采取什么步驟?查看答案
試題參考答案:A
信管網訂閱號
信管網視頻號
信管網抖音號
溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網軟考課程由信管網依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |