A project is near completion and a team member report to project manager that there is an issue which will impact an important deadline. The weekly status report will be sent tomorrow to the major stakeholders. What should the project manager do next step?
A、Update the issue log, inform the sponsor, and use escalation process to report a possible delay to the stakeholders.
B、Inform the stakeholder in the weekly status report, discuss possible solutions with the stakeholders and request budget and schedule extensions.
C、Verify if this issue is in the risk plan, if it is not, include it and develop a mitigation plan.
D、Update the issue log, involve all the people that can help to solve the issue, and communicate the issue to the stakeholders.
我的答案與分析 查看全部答題與分析 | |
|
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習,滿足不同學(xué)員考證需求,降低課程學(xué)習難度,使學(xué)習效果事半功倍。