2008年上半年
The (71) is a general description of the architecture of a workflow
management system used by the WFMC, in which the main components and the
associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (72).
(71)A. waterfall model B. workflow reference model
C. evolutionary model D. spiral model
(72)A. workflow engines B. processes
C. workflow threads D. tasks

The project maintains a current and approved set of requirements over the life of the project by doing the following:
• (73) all changes to the requirements
• Maintaining the relationships among the requirements, the project plans,
and the work products
• ……
(73)A. Monitoring B. Managing C. Gathering D. Reducing

The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result of this analysis and dialog is an (74)set of requirements.
(74)A.agreed-to B.agree-to
C.agreed-to-do D.agree-with

During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.
(75)A. proceedings B. controls
C. forecasting’s D. prelibations

2008年下半年
Define Activities is the process of identifying the specific actions to be performed to produce the (71).
(71)A. project elements B. work drafts
C. work package D. project deliverables
Project work packages are typically decomposed into smaller components called activities to provide a basis for (72), scheduling, executing, and monitoring and controlling the project work.
(72)A. reviewing B. estimating C. auditing D. expecting

● The Estimate Activity Resource process is closely coordinated with the (73)process.
(73)A. Estimate Costs B. Sequence Activities
C. Plan Communications D. Conduct Procurements

● Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.
(74)A. milestone B. baseline C. quality D. work

●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.
(75)A. analyze B. track C. level D. extend 

2008年上半年:(71) B (72) A (73) B (74)A (75)B

2008年下半年:(71) D (72) B (73) A (74)D (75)B
 

[1]   [2]   [3]   [4]   [5]   
掃碼關注公眾號

溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!

信管網致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。

信管網軟考課程由信管網依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。

相關內容

發(fā)表評論  查看完整評論