2009年上半年
Many of the activities performed during the preliminary investigation are still being conducted in (71), but in much greater depth than before. During this phase, the analyst must become fully aware of the(72) and must develop enough knowledge about the(73) and the existing systems to enable an effective solution to be proposed and implemented. Besides the (74) for process and data of current system, the deliverable from this phase also includes the(75)for the proposed system.
(71)A. analysis phase B. design phase
C. implementation phase D. maintenance phase
(72)A. main symptom B. root problem
C. final blueprint D. data specification
(73)A. hardware environment B. testing environment
C. software environment D. business environment
(74)A. logical models B. physical models
C. design models D. implementation models
(75)A. hardware and software specification B. system performance specification
C. formal requirements definition D. general problem statement
2009年下半年
The (71) process ascertains which risks have the potential of affecting the project
and ics. documenting the risks' characteristics。
(71)A. Risk Identification B. Quantitative Risk Analysis
C. Qualitative Risk Analysis D. Risk Monitoring and Control
● The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal of the plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies – (72), Transfer, Mite gate.
(72)A. Challeng B. Exploit
C. Avoid D. Enhance igate.
● (73) is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
(73) A. Method B. Polymorphism
C. Inheritance D. Encapsulation
● The Unified Modeling Language is a standard graphical language for modeling object-oriented software. (74)can show the behavior of systems in terms of how objects interact with each other.
(74)A. Class diagram B. Component diagram
C. Sequence diagram D. Use case diagram
● The creation of a work breakdown structure (WBS) is the process of (75)the major
Project deliverables.
(75)A. subdividing B. assessing
C. planning D. integrating
2009年上半年:(71) A (72) B (73) D (74)A (75)C
2009年下半年:(71) A (72) C (73) B (74)C (75)A