The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables.
A、subdividing
B、assessing
C、planning
D、integrating
創(chuàng)建工作分解結構是分解項目可交付物的過程。
選項A是分解,選項B是估算,選項C是計劃,選項D是整合。
Many of the activities performed during the preliminary investigation are still being conducted in ( ), but in much greater depth than before. During this phase, the analyst must become fully aware of the(-)and must develop enough knowledge about the(-)and the existing systems to enable an effective solution to be proposed and implemented.Besides the(-)for process and data of current system, the deliverable from this phase also includes the(-)for the proposed system.
A、analysis phase
B、design phase
C、implementation phase
D、maintenance phase
在初步調研時完成的許多活動在分析階段還要繼續(xù)進行,只是比以前更深入地去做。在這個分析階段,系統(tǒng)分析師一定要充分注意到問題的根源,并且充分掌握關于業(yè)務環(huán)境和現(xiàn)行系統(tǒng)的知識,以提交和實施一個有效的解決方案。除了提交現(xiàn)行系統(tǒng)的過程和數(shù)據(jù)的邏輯模型外,這一分析階段的交付物還包括推薦系統(tǒng)的正式需求定義。
英語日積月累
( )is primarily concerned with defining and controlling what is and is not included in the project.
A、Project Time Management
B、Project Cost Management
C、Project Scope management
D、Project Communications Management
( )是最先定義和決定項目中包含哪些內容和確定邊界的。
A、項目時間管理
B、項目成本管理
C、項目范圍管理
D、項目溝通管理
Primarily:首先
Concerned:有關
英語日積月累
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A、assign change tasks to project members
B、call a meeting of the configuration control board
C、change the scope baseline
D、postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
項目經理認為調整項目范圍可以給客戶提供增值的服務,項目經理應該( )。
A、安排任務變更到項目成員
B、召集變更控制委員會會議
C、變更項目基線
D、按照原先的基線,在確定完成一項改進項目會得到客戶的相應資金前,暫緩修改
Modify:改變
added value service:增值服務
assign:安排
postpone:延緩
separate:分開的
enhancement:增加
funded:(為某一特定目的給予的)資金
according:依照