第1題:
Estimating schedule activity costs involves developing an(1 )of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of (2 )to facilitate comparisons both within and across projects. The(3 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
(1)A. accuracy B. approximation C. specification D. summary
(2)A. activity B. work C. currency D. time
(3)A. project scope statement
B. statement of work
C. project management plan
D. project policy
參考答案:B、C、A
解析與討論:http://m.xiexiliangjiufa.com/st/61.html
第2題:
The( )defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
參考答案:B
解析與討論:http://m.xiexiliangjiufa.com/st/127.html
第3題:
在滾動式計劃中,( )。
A.關(guān)注長期目標,允許短期目標作為持續(xù)活動的一部分進行滾動
B.近期要完成的工作在工作分解結(jié)構(gòu)最下層詳細規(guī)劃
C.遠期要完成的工作在工作分解結(jié)構(gòu)最下層詳細規(guī)劃
D.為了保證項目里程碑,在戰(zhàn)略計劃階段做好一系列詳細的活動計劃
參考答案:B
解析與討論:http://m.xiexiliangjiufa.com/st/307.html
第4題:
某五星級酒店公開招標建設(shè)一套“無線網(wǎng)絡(luò)”系統(tǒng),以滿足商務(wù)客人在酒店范圍內(nèi)隨時隨地高速訪問Internet的需要。該項目最適合采用的無線網(wǎng)絡(luò)技術(shù)是( )。
A.WiFi
B.Bluetooth
C.BlueRay
D.GPRS
參考答案:A
解析與討論:http://m.xiexiliangjiufa.com/st/964.html
第5題:
以下關(guān)于數(shù)據(jù)倉庫與數(shù)據(jù)庫的敘述中,( )是正確的。
A.數(shù)據(jù)倉庫的數(shù)據(jù)高度結(jié)構(gòu)化、復雜、適合操作計算;而數(shù)據(jù)庫的數(shù)據(jù)結(jié)構(gòu)比較簡單,適合分析
B.數(shù)據(jù)倉庫的數(shù)據(jù)是歷史的、歸檔的、處理過的數(shù)據(jù);數(shù)據(jù)庫的數(shù)據(jù)反映當前的數(shù)據(jù)
C.數(shù)據(jù)倉庫中的數(shù)據(jù)使用頻率較高;數(shù)據(jù)庫中的數(shù)據(jù)使用頻率較低
D.數(shù)據(jù)倉庫中的數(shù)據(jù)是動態(tài)變化的,可以直接更新;數(shù)據(jù)庫中的數(shù)據(jù)是靜態(tài)的,不能直接更新
參考答案:B
解析與討論:http://m.xiexiliangjiufa.com/st/1198.html
第6題:
以下關(guān)于采購工作說明書的敘述中,( )是錯誤的。
A. 采購說明書與項目范圍基準沒有關(guān)系
B. 采購工作說明書與項目的工作說明書不同
C. 應在編制采購計劃的過程中編寫采購工作說明書
D. 采購工作說明書定義了與項目合同相關(guān)的范圍
參考答案:A
解析與討論:http://m.xiexiliangjiufa.com/st/1228.html
第7題:
以太網(wǎng)100BASE-TX 標準規(guī)定的傳輸介質(zhì)是( )
A. 3類UTP
B. 5 類UTP
C. 單模光纖
D. 多模光纖
參考答案:B
解析與討論:http://m.xiexiliangjiufa.com/st/1328.html
第8題:
信息系統(tǒng)開發(fā)方法有很多種,開發(fā)人員可以根據(jù)項目的需要選擇一種適合的開發(fā)方法,其中把整個系統(tǒng)的開發(fā)過程分為若干階段,然后一步一步地依次進行開發(fā)的方法稱為( )
A、結(jié)構(gòu)化方法
B、面向?qū)ο蠓椒?br />
C、原型方法
D、瀑布模型方法
參考答案:A
解析與討論:http://m.xiexiliangjiufa.com/st/1961.html
第9題:
根據(jù)GB/t11457-2006的規(guī)定,使客戶能確認是否接受系統(tǒng)的正式測試為( )。
A.合格性測試 B.驗收測試 C.運行測試 D.系統(tǒng)測試
參考答案:B
解析與討論:http://m.xiexiliangjiufa.com/st/3434.html
第10題:
風險轉(zhuǎn)移是設(shè)法將風險的后果連同應對的責任轉(zhuǎn)移到他方的風險應對措施,( )不屬于風險轉(zhuǎn)移的措施
A 履約保證書
B 購買保險
C 第三方擔保
D 改變工藝流程
參考答案:D
解析與討論:http://m.xiexiliangjiufa.com/st/4341.html
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |