A newly assigned project manager learns that the project likely to fail because there are too many stakeholder who all disagree. What should the project manager do?
新任命的項(xiàng)目經(jīng)理得知,因?yàn)橛刑嘞嚓P(guān)方意見不一致,項(xiàng)目可能會(huì)失敗。項(xiàng)目經(jīng)理應(yīng)該怎么做?
A.meet with all project stakeholder to try and align their differences與所有相關(guān)方開會(huì),嘗試調(diào)整他們的差異
B.Separately meet with each stakeholder to try and understand their individual viewpoints與每位相關(guān)方分別開會(huì),嘗試?yán)斫馑麄兏髯缘挠^點(diǎn)
C.Develop a stakeholder engagement plan and address stakeholder concerned制定相關(guān)方參與計(jì)劃并解決相關(guān)方的顧慮
D.Update the stakeholder engagement plan and send it to all stakeholder.更新相關(guān)方參與計(jì)劃,并將其發(fā)送給所有相關(guān)方
信管網(wǎng)參考答案:C
信管網(wǎng)解析:
C是參考答案。與相關(guān)方互動(dòng)之前首先制定相關(guān)方參與計(jì)劃,根據(jù)計(jì)劃接洽相關(guān)方,解決問(wèn)題。 參考13.2過(guò)程描述。
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)生了質(zhì)量監(jiān)督,變更控制委員會(huì)(CCB)批準(zhǔn)了所產(chǎn)
一家組織在項(xiàng)目執(zhí)行階段發(fā)生變化,結(jié)果,一位關(guān)鍵相關(guān)
一個(gè)大型項(xiàng)目已經(jīng)完工。作為組織過(guò)程資產(chǎn)的一部分,項(xiàng)
在一個(gè)大型項(xiàng)目中,項(xiàng)目經(jīng)理決定將風(fēng)險(xiǎn)轉(zhuǎn)移給供應(yīng)商是
在項(xiàng)目開始時(shí),項(xiàng)目發(fā)起人宣布可用資金比原計(jì)劃少5%
公司聘用一名項(xiàng)目經(jīng)理來(lái)協(xié)調(diào)一個(gè)期限緊迫的敏捷項(xiàng)目,
在項(xiàng)目的質(zhì)量審查期間,團(tuán)隊(duì)討論了對(duì)當(dāng)前質(zhì)量管理計(jì)劃
根據(jù)批準(zhǔn)的商業(yè)論證,項(xiàng)目必須在12個(gè)月內(nèi)完成,以最
一個(gè)大型項(xiàng)目正處于收尾階段,客戶拒絕簽署同意項(xiàng)目可
項(xiàng)目經(jīng)理正在管理一個(gè)項(xiàng)目,向眾多機(jī)構(gòu)交付新的報(bào)告產(chǎn)
發(fā)表評(píng)論 查看完整評(píng)論 | |