A project manager is reviewing a status report that shows a schedule delay and cost overruns. This report must be presented to the steering committee in two weeks. From past experience, the project manager knows which stakeholders will be very difficult, what should the project manager do?
項(xiàng)目經(jīng)理正在審查狀態(tài)報(bào)告,該報(bào)告顯示進(jìn)度延遲和成本超支,該報(bào)告必須在兩周內(nèi)提交給指導(dǎo)委員會(huì),根據(jù)過(guò)去的經(jīng)驗(yàn),項(xiàng)目經(jīng)理知道哪些相關(guān)方會(huì)很挑剔,項(xiàng)目經(jīng)理應(yīng)該怎么做?
A.meet with difficult stakeholders to explain the reasons for the delays and cost overrun與挑剔的相關(guān)方開(kāi)會(huì),解釋延遲和成本超支的原因
B.Collect additional details from the project team to clarify the reasons for the delay and cost overruns收集項(xiàng)目團(tuán)隊(duì)的其他詳細(xì)信息,以澄清延遲和成本超支的原因
C.Quickly identify corrective actions that can be implemented to improve the status report快速識(shí)別可以實(shí)施的糾正措施,以改進(jìn)狀態(tài)報(bào)告
D.Contact management to seek help with dealing with the difficult stakeholders聯(lián)系管理層尋求如何與挑剔的相關(guān)方打交道的幫助
信管網(wǎng)參考答案:B
信管網(wǎng)解析:
B是參考答案。問(wèn)題解決流程中需要收集詳細(xì)信息,理解根本原因,然后識(shí)別應(yīng)對(duì)措施。在實(shí)施A或C之前應(yīng)該首先做B,全面理解問(wèn)題本身。參考問(wèn)題解決流程9.6.2.2
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
一位新項(xiàng)目經(jīng)理負(fù)責(zé)管理一個(gè)處于規(guī)劃階段之后的項(xiàng)目。
在項(xiàng)目執(zhí)行期間,項(xiàng)目經(jīng)理注意到正在使用項(xiàng)目管理軟件
新任命的項(xiàng)目經(jīng)理得知,因?yàn)橛刑嘞嚓P(guān)方意見(jiàn)不一致,
發(fā)生了質(zhì)量監(jiān)督,變更控制委員會(huì)(CCB)批準(zhǔn)了所產(chǎn)
一家組織在項(xiàng)目執(zhí)行階段發(fā)生變化,結(jié)果,一位關(guān)鍵相關(guān)
一個(gè)大型項(xiàng)目已經(jīng)完工。作為組織過(guò)程資產(chǎn)的一部分,項(xiàng)
在一個(gè)大型項(xiàng)目中,項(xiàng)目經(jīng)理決定將風(fēng)險(xiǎn)轉(zhuǎn)移給供應(yīng)商是
在項(xiàng)目開(kāi)始時(shí),項(xiàng)目發(fā)起人宣布可用資金比原計(jì)劃少5%
公司聘用一名項(xiàng)目經(jīng)理來(lái)協(xié)調(diào)一個(gè)期限緊迫的敏捷項(xiàng)目,
在項(xiàng)目的質(zhì)量審查期間,團(tuán)隊(duì)討論了對(duì)當(dāng)前質(zhì)量管理計(jì)劃
發(fā)表評(píng)論 查看完整評(píng)論 | |